Tunnel-14 breakthrough boosts Rishikesh-Karanprayag rail link
In Short
RVNL links 6.59 km bore through tricky hills in Rudraprayag

Tunnel-14 breakthrough boosts Rishikesh-Karanprayag rail link
Hyderabad: RVNL has completed the main tunnel breakthrough for the 6.59 km Tunnel-14 on the Rishikesh–Karanprayag rail project in Rudraprayag district. Crews joined 4.7 km excavated from Portal-1 at Sumerpur with 1.79 km driven from Portal-2 at Marora. The milestone came on Friday after years of careful work across tough terrain.
At Portal-1, teams excavated 110 metres of triple-track tunnel through loose soil beneath inhabited areas. Overburden reached 20 to 30 metres in this stretch. Engineers used pre-excavation and multi-drifting methods to keep ground movement under control while working under local homes.
At Portal-2, crews stabilised the slope with 30 to 35 metre deep micropiles, 15 to 20 metre rock bolts, and consolidation grouting. That ground work allowed the main drive to start in March 2024. Before starting, authorities resolved ground settlement issues at Marora and completed land and home acquisition.
Work near both ends followed strict safety limits to protect nearby settlements. Crews carried out about 100 metres of mechanical excavation at Portal-2 and kept controlled blasting strictly to daytime hours near both portals.
Long underground work required steady air and heat control. Teams ran specialised ventilation systems to supply fresh air and regulate temperatures along the 4.7 km drive from Portal-1.
The breakthrough marks major progress on a mountain railway built to improve travel across Uttarakhand. Further lining and track works will follow before trains can run through the completed bore. Engineers used modern support methods to tackle weak rock and soft ground safely. Project officials say careful planning helped crews meet safety rules while keeping the schedule moving forward for local residents and commuters across the region.