APSPDCL CMD orders RDSS works by Dec-end

In Short

APSPDCL CMD Siva Sankar Lotheti orders completion of pending RDSS works and 33 kV/11 kV feeder bifurcations by December end to boost power reliability.

APSPDCL Chairman and Managing Director Siva Sankar Lotheti addressing a review meeting in Tirupati on Thursday
X

APSPDCL Chairman and Managing Director Siva Sankar Lotheti addressing a review meeting in Tirupati on Thursday

Font size
FOLLOW ON Google News

Andhra Pradesh Southern Power Distribution Company Limited (APSPDCL) Chairman and Managing Director Siva Sankar Lotheti has directed officials and contractors to accelerate all ongoing works under Revamped Distribution Sector Scheme (RDSS). He instructed them to complete pending projects by the end of December to ensure consumers receive better-quality and more reliable power supply.

While reviewing progress of the works during a video conference on Thursday, the CMD particularly stressed the need to complete bifurcation of 33 kV and 11 kV feeders. Of the total 3,015 feeder bifurcation works taken up in APSPDCL limits, 2,153 works were completed as on November 26. The CMD asked officials concerned to complete the remaining works without further delay.

Stating that 54 of the 72 works related to bifurcation of 33 kV feeders have been completed, he told the officials to complete the remaining 18 works at the earliest. Under the second phase of the scheme, 465 additional 11 kV feeder bifurcation works have been taken up and 63 of these works have been completed. Lotheti directed officials and contractors to expedite the remaining works and finish them within the stipulated deadline.

The CMD also asked officials to resolve problems faced during the execution of works. They were instructed to obtain necessary permissions from Forest, National Highways and Railway departments quickly. He said officials and contractors should coordinate closely to avoid delays and ensure timely completion of all RDSS works.

Lotheti further asked officials to monitor progress of works continuously at field level. He said there should be no delay in supply of electric poles and other materials required for works. Contractors were told to deploy additional staff and work teams wherever necessary to meet the deadline.

Vani Mallela is a Staff Reporter at The Hans India and an accomplished journalist and content creator from the erstwhile Chittoor district. With over 16 years of professional experience, she has built a strong reputation for covering crime, politics, and entertainment, delivering stories that are accurate, engaging, and impactful. She holds a postgraduate degree from Sri Venkateswara University and received professional journalism training at Rachana Journalism College, Hyderabad, with a focus on science and mass communication. Her expertise includes field reporting, investigative journalism, fact-checking, and source development, enabling her to produce balanced and credible reports under tight deadlines. Vani is recognised for her sharp news sense, concise writing style, and ability to uncover compelling human-interest stories that reflect the voices and concerns of local communities. Her extensive knowledge of the Tirupati region, coupled with her diverse family background and broad cultural exposure, brings depth, empathy, and context to her reporting. A dedicated journalist committed to ethical and responsible reporting, Vani continually enhances her knowledge by keeping abreast of current affairs through regular newspaper reading and extensive research. Her professionalism, accuracy, and passion for storytelling have made her a respected voice in regional journalism.